Coastal Mountain Excavations

stakeholder on the project, as they had

to coordinate the rail shutdown in order

to create the 24 hour window where the

company delivered majority of the proj-

ect.

According to Matt, Coastal Moun-

tain Excavations was able to pull that

project off, despite the tight time-frame,

due to the experience and co-ordination

of their team.

“Everyone had their work plan di-

alled in,” he says. “We communicated to

every player that was involved – from the

guys on shovels, to the guys running the

big excavators and the rock trucks, to the

crane guys who brought the culvert in, to

everyone else. The project probably in-

volved 100 different people in a 24 hour

period, and everyone did their job. It was

an amazing installation that went very

well.”