City of Moncton | 7
developed with one of the goals focusing on
the creation of a detention basin; a system al-
lowing water to collect within a dry basin/
pond and slowly bleeding it off downstream
so they are not flooding anybody else down-
stream. The process has called for review-
ing an area where flooding had occurred,
in turn, hydraulic capacity analysis was per-
formed and RFP’s went out to a consortium
of key integral businesses which included
the Moncton Infrastructure Group. Made
up of Genivar, EXP, Crandall Engineering,
and Hatch Mott McDonald, the group has
been successful through five phases of the
Master plan with another six to go. One of
the objectives of the most recent project is
ensuring that both the combined system and
separated system are handled by a controlled
device which will only permit the amount of
water into their systems that can be handled
without their systems surcharging. Another
integral area, is looking at improvements to
increase sewer capacity issues and better fa-
cilitate drain release (i.e. if there is a sag in